Robotics in business

How WST Fab adapted its robot cell to new parts

An order disappears, but the new cell stays useful: what WST Fab changed and how to assess the cost of switching to another part.

Nivama Robotics5 min read

On the day WST Fab received its new robot cell, the customer order it had been designed for fell through. The US manufacturer had ordered a machine-tending system configured for a particular part. Without that part, the new equipment risked having no work. According to the published case study, the company’s own team reconfigured the cell within days: it changed the program, adapted the fixtures and produced new grippers using 3D printing.

The UR10e cell was subsequently used for twelve different parts. Integrator PCC Robotics had supplied the arm, tooling, base, material staging and connection to the CNC machine. Training was part of the handover. These details come from the Universal Robots case study, which does not provide a publication date or detailed production statistics.

The case describes a specific kind of flexibility: equipment already installed could be reassigned to other orders. That required more than changing a part name in the program. The robot still needed a defined starting point, a suitable grip and a reliable handover to the machine.

What actually changes with a different part

Consider a simplified machine-tending cycle, offered here as an explanation rather than additional information about WST’s installation. Raw parts sit on a staging tray. The robot picks one up, places it in the open machine and enables machining to start. After machining, it removes the finished part and places it in a second holder. Every handover point must work with the new part.

If a business switches from a short workpiece to a longer one, several changes may be needed together. The staging area needs more space. The gripper must hold the part at a suitable point. The path through the machine door must remain clear despite the protruding end. Inside the machine, appropriate workholding must position the part correctly for machining.

The motion program is only one element. A new gripper may alter the overall dimensions of the moving assembly. A different staging tray shifts the pickup position. Modified workholding changes the point at which the part is handed over. Only when these changes fit together can the cycle be repeated and checked.

According to the manufacturer, adaptable fixtures and grippers made by WST helped with this project. Dual grippers were also used to remove a finished part and insert a new blank. The source thus identifies concrete elements of the changeover, but does not list all twelve parts or their individual cycle times. It cannot establish a general changeover time for arbitrary products.

For a new installation, this suggests a practical planning question: which family of parts should it be able to process in future? The answer might cover several similar shapes with different lengths. Such a bounded task is easier to verify than a requirement that the robot should eventually handle “everything”. Each additional variant needs defined conditions for presentation, handling and machining.

Flexibility needs skills and a calculation

A second issue is the integrator’s handover. Anyone expected to set up a variant in-house needs program access and clear information about the interfaces. In the simplified example, the team needs to know when the machine is ready, how a failed pickup is detected and which state permits a restart. Otherwise, every change remains dependent on the original supplier.

A useful acceptance exercise could work as follows: after the first part has been configured, an employee performs an agreed changeover using the supplied documentation. The time required, unresolved questions and assistance needed are recorded. This is a proposed acceptance exercise, not a test documented in the WST case study. It makes the promised adaptability verifiable through an observable procedure.

The economics depend on both the hours the cell can spend on suitable orders and the cost of adapting it. Take an illustrative example: a changeover requires four working hours and €300 for new gripper fingers. At an assumed internal cost of €60 per hour, the initial expense is €540. Other costs, such as machine downtime or an additional inspection, would need to be added separately.

If the new order then enables 30 usable machine hours, that one-off changeover works out at €18 per gained hour. For only three hours, it would be €180. The same technical modification therefore deserves a different assessment for a recurring order than for a very small, one-off batch. This calculation does not establish profitability: actual manufacturing costs and revenue, among other figures, are missing.

Before purchasing, it is therefore useful to examine several realistic orders. For each variant, the required modifications can be compared with batch size and expected recurrence. As a structured starting point, Fraunhofer IPK describes assessing individual process steps: first record the existing workflow, then assess the technical feasibility of critical functions and develop an economically appropriate scenario.

At WST Fab, the cell remained useful after the original order disappeared. The published account demonstrates a successful response to changing demand, but does not establish a generally applicable payback period. The transferable lesson concerns preparation: a cell becomes adaptable when tooling, part presentation, machine integration and the team’s skills are planned together around several concrete tasks.

Sources checked: 12 November 2026. The company case is based on a manufacturer report. The additional process and cost examples are explicitly illustrative.